Direct Drive Work Plan
Ü
Schedule by December 15th
Chassis Dyno built and test plan complete
Ü
Scheduled dyno testing (cleared through Dan)
Ü
Gear Design complete with manufacturer order completed (custom or off the shelf)
Ü
Shaft Design completed
Ü
Bearings selected and ordered
Ü
Preliminary gear housing designed
Schedule by Spring Break
Ü
System
Design completed- Jan. 15
Ü
Testing of Chain Drive- Jan. 19
Ü
Manufacturing completed- Feb. 2
Ü
Installation and Testing of RMI- Feb.12
Ü
Installation and Testing of Optimized by- Feb. 12