Clearwater-Aid

Advisor Report 2/15/07

Advisor Report 2/12/07
Team Clearwater-aid
Success for the past week

#1 Coli-form testing Kit are on there way.
#2 the designs are all very close to being finished. Moral is still high and the attitude of the team is that failure is not an option.
Tasks completed for the past week
Owner
Support
Description of outcomes
Value to the project
Delivery date
Percent done
Deliver to
Diana
Whit
Constructed fully functional design
Valid fully working designs that can be taken to Africa
1/30/07
90%
Late
Whit
Mark
Nick
Constructed fully functional design
Valid fully working designs that can be taken to Africa
1/30/07
90%
Late
Whit
G
Matt
 Constructed fully
functional design
Valid fully working designs that can be taken to Africa
1/30/07
60%
Late
Whit
Whit
G,  Diana
Meet this Monday or wed. with Todd in the ceramics department on open pit firing techniques and create an instructional document
Ceramics are complex and take care to create, Todd’s experience  is a valuable resource
2/7/07
100%
Don/Whit
Issues and challenges for the coming week
#1 just over a week before our trip to Africa and not one of the sub teams came through with there fully completed design. This is very troubling because we need to give them options with our designs and we must be able to defend the designs.
#2 there is an ethical dilemma involved in the completion of our designs. We need to prove that these design will work in Moscow if there is any chance of making it work in Kenya.
#3 The documentation for the completed tasks needs great improvement. Completing a task is worthless if there is no documentation.
#4 The team needs to be able to trust each other to get things done. Time is scarce right now and it is difficult enough to get your own designs without encouraging other to press forward. This is where personal ownership becomes very important. We must take responsibility to complete the tasks in a timely fashion.

WBS for the coming week

Owner
Support
Description of outcomes
Value to the project
Delivery date
Percent complete
Deliver to
Whit
Diana
Data Bio/Mech on the designs
Proves effectiveness of the design in meeting specs
2/8/07late
2/15/07
pending
Don/Whit
Nick
Mark
Data Bio/Mech on the designs
Proves effectiveness of the design in meeting specs
2/8/07late
2/15/07
pending
Don/Whit
Matt
G
Data Bio/Mech on the designs
Proves effectiveness of the design in meeting specs
2/8/07late
2/15/07
pending
Don/Whit
Diana
Matt
A full report analyzing the biological content of turbid water before and after moringa seed flocculation
This process is known to remove biological content even without filtration. Quantify this
2/9/07late
2/15/07
Don/Whit
Mark
Updated website. Have our website added to the capstone page. we are the only team without it
 Exposes our project and brings the website up to the standard of the other teams
2/16/07
Don
Diana
Whit
Constructed fully functional design
Valid fully working designs that can be taken to Africa
1/30/07
2/15/07
90%
Priority
Set meeting with Don
Mark
Nick
Constructed fully functional design
Valid fully working designs that can be taken to Africa
1/30/07
2/15/07
90%
Priority
Set meeting with Don
G
Matt
 Constructed fully
functional design
Valid fully working designs that can be taken to Africa
1/30/07
2/15/07
60%
Priority
Set meeting with Don

Attachments

NameVersionSizeDateUser
Advisor Report 4.doc1455683/5/07 4:47 PMDianaRudeck
Advisor Report 3/5/07
 
 
 

Last Modified 2/12/07 10:52 AM