Sleep Sound

Work Breakdown

Who Does What:

Project Start Date: Thu 9/7/06
Project Finish Date: Fri 4/20/07

 

Task_Data

ID
Task_Name
DurationStart_DateFinish_DatePredecessorsResource_Names
1
Start
0 daysThu 9/7/06Thu 9/7/06  
2
Project Definition
21 days?Thu 9/7/06Thu 10/5/061 
3
Team Formation
1 dayThu 9/7/06Thu 9/7/06 Team
4
Establish Team Roles
1 day?Thu 9/7/06Thu 9/7/06 Team
5
Team Manager
1 day?Thu 9/7/06Thu 9/7/06 Lloyd
6
Determine Customer Needs
18 daysTue 9/12/06Thu 10/5/06  
7
Contact Client
1 dayWed 9/13/06Wed 9/13/06 Chris
8
Write Up Questions For Client
7 daysTue 9/12/06Wed 9/20/06 Team
9
Interview Client
1 dayThu 9/21/06Thu 9/21/06 Team
10
Write Up Client Need
7 daysWed 9/27/06Thu 10/5/06 Team
11
Establish Target Specifications
7 daysThu 9/7/06Fri 9/15/06 Team
12      
13
Conceptual Design
26 days?Thu 9/21/06Thu 10/26/06  
14
Research/Knowledge Areas
16 days?Thu 9/21/06Thu 10/12/06 Team
15
Contact SIDS Organizations
18 days?Tue 10/3/06Thu 10/26/06 Jennifer
16
Visit Dr. Forstead in Pullman
1 day?Fri 10/13/06Fri 10/13/06 Jennifer,Bart
17
Visit Gritman Sleep Center
1 day?Wed 10/11/06Wed 10/11/06 Colby,Jeff,Lloyd
18
Under the Infant Monitors
16 days?Wed 10/4/06Wed 10/25/06  
19
Prototype Strain Gage
16 days?Wed 10/4/06Wed 10/25/06  
20
Phase I (strain gage protype)
1 day?Wed 10/4/06Wed 10/4/06 Chris,Colby Bart,Lloyd,Jeff
21
Phase II (potential)
1 day?Wed 10/25/06Wed 10/25/0620 
22
Prototype Pressure Sensor
7 days?Wed 10/11/06Thu 10/19/06  
23
Phase I
1 day?Wed 10/11/06Wed 10/11/06 Jennifer,Chris,Bart
24
Phase II
6 days?Thu 10/12/06Thu 10/19/0623Chris,Colby,Bart
25
On the Infant Monitors
11 days?Thu 10/12/06Thu 10/26/06  
26
Prototype Inductance Monitor
11 days?Thu 10/12/06Thu 10/26/06  
27
Phase I
6 days?Thu 10/12/06Thu 10/19/06 Lloyd,Jeff
28
Phase II
5 days?Fri 10/20/06Thu 10/26/0627Lloyd,Jeff
29
Over the Infant Monitors
8 days?Tue 10/17/06Thu 10/26/06  
30
Additional Prototyping
8 days?Tue 10/17/06Thu 10/26/06  
31
Conceptual Design Review
1 day?Thu 10/26/06Thu 10/26/06 Team
32      
33
Detailed Design
125 days?Mon 10/30/06Fri 4/20/07 Team
34
Fabrication
66 days?Mon 10/30/06Mon 1/29/07  
35
Move Forward With A Single Monitoring System
1 day?Mon 10/30/06Mon 10/30/06  
36
System Design
30 days?Mon 10/30/06Fri 12/8/06  
37
Finalize Project Goal State
30 days?Mon 10/30/06Fri 12/8/06  
38
Finalize Project Road Map
30 days?Mon 10/30/06Fri 12/8/06  
39
Finalize Proposal
10 days?Mon 11/20/06Fri 12/1/06  
40
Develop A Functional Monitor Design
25 days?Mon 10/30/06Fri 12/1/06  
41
Snapshot Day
1 day?Fri 12/1/06Fri 12/1/06  
42
Detail Design
11 days?Mon 1/15/07Mon 1/29/07  
43
Prototype Refinement
11 days?Mon 1/15/07Mon 1/29/07  
44      
45
Validation
70 days?Mon 1/15/07Fri 4/20/07  
46
Validate Peformance of Monitor
11 days?Mon 1/15/07Mon 1/29/07  
47
Adjust/Debug Problems
49 days?Wed 2/7/07Mon 4/16/07  
48
Final Project Report
34 days?Tue 3/6/07Fri 4/20/07  
49
Delivery of Monitor
1 day?Fri 4/20/07Fri 4/20/07  
50
End
1 day?Fri 4/20/07Fri 4/20/07  