april12meetingTeam Meeting April 12th, 2007 I. Plans for wrapping up project deliverables. A. Final report is due Wed, April 25th. - Colby is working on it. B. The SleepSound web page needs to migrate to the Capstone course page. - Lloyd will work on this after the prototype is working. C. We will produce a final laminated project poster and a final design presentation to be finalized by April 27th.
|