I.  Assessment
   
A.  The need for further documentation of scheduling / individual action items has allready     been identified
  1.  Objective:  Create a new section of the team website as a dedicated log of action items / action item time frames and completion status. 
Colby will be responsible for setting up and maintaining the new website section
Each completed task will also be selected as a link to a page, displaying information about the task results.   
 
II.  Project Action Items
 A.  Jeff - 2 weeks - Get the sensor to effectively transmit the signal to a reciever
B.  Lloyd - 2 weeks - Order the micro controller and prepare it for implementation into the design.
C.  Bart - 1 week - Finish the wire stress model.
D.  Jennifer - 1 week - Take measurements of the robotic infant mode at the hospital and gather some information on injection molding. 
E.  Jennifer, Bart, Colby, Chris - 1 week - provide a rough draft design for a new iteration of the variable inductor / infant sleep wear shirt combination.   

 
 
 