Project Start:
Project Finish:
Wed 12/13/06
Mon 4/30/07


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Network
79 daysWed 1/10/07Mon 4/30/07Kyle Schiepan0%
2
Learn Master/Slave Communication
5 daysWed 1/10/07Tue 1/16/07 0%
3
Adapt Code to Master/Slave Communication
15 daysWed 1/17/07Tue 2/6/07 0%
4
Research Previous Year Issues
15 daysWed 2/7/07Tue 2/27/07 0%
5
Troubleshoot Previous Year Issues
44 daysWed 2/28/07Mon 4/30/07 0%
6      
7
Remote Pedestrian Button
79 daysWed 1/10/07Mon 4/30/07Gabriel DeRuwe0%
8
Breadboard New Parts
3 daysWed 1/10/07Fri 1/12/07 0%
9
Testing and Finilization of Design
15 daysMon 1/15/07Fri 2/2/07 0%
10
PCB Ordered
0 daysFri 2/2/07Fri 2/2/07 0%
11
RFID Research/Design
35 daysMon 1/15/07Fri 3/2/07 0%
12
Add new Device to Network
45 daysMon 1/15/07Fri 3/16/07 0%
13
Populate PCB
2 daysMon 3/19/07Tue 3/20/07 0%
14
Test PCB
8 daysWed 3/21/07Fri 3/30/07 0%
15
Integration
21 daysMon 4/2/07Mon 4/30/07 0%
16      
17
System Monitor
79 daysWed 1/10/07Mon 4/30/07Bryan Humphrey0%
18
Decide on Data Logger
17 daysWed 1/10/07Thu 2/1/07 0%
19
Order Data Logger
17 daysWed 1/10/07Thu 2/1/07 0%
20
Develop Optical Sensor
11 daysThu 2/1/07Thu 2/15/07 0%
21
Implement PnP sensor system
10 daysFri 2/16/07Thu 3/1/07 0%
22
Integrate sensor systems with data logger
10 daysFri 3/2/07Thu 3/15/07 0%
23
Implement interface with data logger
22 daysFri 3/16/07Mon 4/16/07 0%
24
Complete System
10 daysTue 4/17/07Mon 4/30/07 0%
25      
26
Smart Pedestrian Button
79 days?Wed 1/10/07Mon 4/30/07Adam Hieb0%
27
Begin Prototyping
16 days?Wed 1/10/07Wed 1/31/07 0%
28
Board Design
8 days?Thu 2/1/07Mon 2/12/07 0%
29
Order PCB
21 days?Tue 2/13/07Tue 3/13/07 0%
30
Integrate Prototype into Network
6 days?Wed 3/14/07Wed 3/21/07 0%
31
Test Prototype
12 days?Thu 3/22/07Fri 4/6/07 0%
32
Integrate All Components
16 days?Mon 4/9/07Mon 4/30/07 0%
33      
34
Countdown Timer
79 days?Wed 1/10/07Mon 4/30/07Dan Miller0%
35
Model System
6 days?Wed 1/10/07Wed 1/17/07 0%
36
Combine Code
11 days?Thu 1/18/07Thu 2/1/07 0%
37
Add new device to Network
11 days?Thu 1/18/07Thu 2/1/07 0%
38
Test
11 days?Fri 2/2/07Fri 2/16/07 0%
39
Update Other Timers
8 days?Mon 2/19/07Wed 2/28/07 0%
40
Integrate into Network
43 days?Thu 3/1/07Mon 4/30/07 0%

Resources


IDNameGroupMax UnitsPeak Units
1Kyle Schiepan 100%100%
2Gabriel DeRuwe 100%100%
3Bryan Humphrey 100%100%
4Adam Hieb 100%100%
5Dan Miller 100%100%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
1NetworkKyle Schiepan632 hrsWed 1/10/07Mon 4/30/070%
7Remote Pedestrian ButtonGabriel DeRuwe632 hrsWed 1/10/07Mon 4/30/070%
17System MonitorBryan Humphrey632 hrsWed 1/10/07Mon 4/30/070%
26Smart Pedestrian ButtonAdam Hieb632 hrsWed 1/10/07Mon 4/30/070%
34Countdown TimerDan Miller632 hrsWed 1/10/07Mon 4/30/070%