| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Network | 79 days | Wed 1/10/07 | Mon 4/30/07 | Kyle Schiepan | 0% |
| 2 | Learn Master/Slave Communication | 5 days | Wed 1/10/07 | Tue 1/16/07 | | 0% |
| 3 | Adapt Code to Master/Slave Communication | 15 days | Wed 1/17/07 | Tue 2/6/07 | | 0% |
| 4 | Research Previous Year Issues | 15 days | Wed 2/7/07 | Tue 2/27/07 | | 0% |
| 5 | Troubleshoot Previous Year Issues | 44 days | Wed 2/28/07 | Mon 4/30/07 | | 0% |
| 6 | | | | | | |
| 7 | Remote Pedestrian Button | 79 days | Wed 1/10/07 | Mon 4/30/07 | Gabriel DeRuwe | 0% |
| 8 | Breadboard New Parts | 3 days | Wed 1/10/07 | Fri 1/12/07 | | 0% |
| 9 | Testing and Finilization of Design | 15 days | Mon 1/15/07 | Fri 2/2/07 | | 0% |
| 10 | PCB Ordered | 0 days | Fri 2/2/07 | Fri 2/2/07 | | 0% |
| 11 | RFID Research/Design | 35 days | Mon 1/15/07 | Fri 3/2/07 | | 0% |
| 12 | Add new Device to Network | 45 days | Mon 1/15/07 | Fri 3/16/07 | | 0% |
| 13 | Populate PCB | 2 days | Mon 3/19/07 | Tue 3/20/07 | | 0% |
| 14 | Test PCB | 8 days | Wed 3/21/07 | Fri 3/30/07 | | 0% |
| 15 | Integration | 21 days | Mon 4/2/07 | Mon 4/30/07 | | 0% |
| 16 | | | | | | |
| 17 | System Monitor | 79 days | Wed 1/10/07 | Mon 4/30/07 | Bryan Humphrey | 0% |
| 18 | Decide on Data Logger | 17 days | Wed 1/10/07 | Thu 2/1/07 | | 0% |
| 19 | Order Data Logger | 17 days | Wed 1/10/07 | Thu 2/1/07 | | 0% |
| 20 | Develop Optical Sensor | 11 days | Thu 2/1/07 | Thu 2/15/07 | | 0% |
| 21 | Implement PnP sensor system | 10 days | Fri 2/16/07 | Thu 3/1/07 | | 0% |
| 22 | Integrate sensor systems with data logger | 10 days | Fri 3/2/07 | Thu 3/15/07 | | 0% |
| 23 | Implement interface with data logger | 22 days | Fri 3/16/07 | Mon 4/16/07 | | 0% |
| 24 | Complete System | 10 days | Tue 4/17/07 | Mon 4/30/07 | | 0% |
| 25 | | | | | | |
| 26 | Smart Pedestrian Button | 79 days? | Wed 1/10/07 | Mon 4/30/07 | Adam Hieb | 0% |
| 27 | Begin Prototyping | 16 days? | Wed 1/10/07 | Wed 1/31/07 | | 0% |
| 28 | Board Design | 8 days? | Thu 2/1/07 | Mon 2/12/07 | | 0% |
| 29 | Order PCB | 21 days? | Tue 2/13/07 | Tue 3/13/07 | | 0% |
| 30 | Integrate Prototype into Network | 6 days? | Wed 3/14/07 | Wed 3/21/07 | | 0% |
| 31 | Test Prototype | 12 days? | Thu 3/22/07 | Fri 4/6/07 | | 0% |
| 32 | Integrate All Components | 16 days? | Mon 4/9/07 | Mon 4/30/07 | | 0% |
| 33 | | | | | | |
| 34 | Countdown Timer | 79 days? | Wed 1/10/07 | Mon 4/30/07 | Dan Miller | 0% |
| 35 | Model System | 6 days? | Wed 1/10/07 | Wed 1/17/07 | | 0% |
| 36 | Combine Code | 11 days? | Thu 1/18/07 | Thu 2/1/07 | | 0% |
| 37 | Add new device to Network | 11 days? | Thu 1/18/07 | Thu 2/1/07 | | 0% |
| 38 | Test | 11 days? | Fri 2/2/07 | Fri 2/16/07 | | 0% |
| 39 | Update Other Timers | 8 days? | Mon 2/19/07 | Wed 2/28/07 | | 0% |
| 40 | Integrate into Network | 43 days? | Thu 3/1/07 | Mon 4/30/07 | | 0% |