October 8th 2007 - Website complete and published
October 28th 2007 - Preliminary Design Review
October 30th 2007 - ONR came down for project update
November 13th 2007 - Design Report Review
November 15th 2007 - Design Review with Bayview at UI Campus
March 1st 2008 - Final Topography decided
March 3rd 2008 - Design a 1/10th Prototype Model of DC-DC Electronics
March 29th 2008 - Parts selected and ordered for prototype
April 11th 2008 - Prototype constructed
April 23rd 2008 - Prototype testing and design finalized