  • TASK DURATION FROM TO RESOURCE
    PHASE 1 - Project Scoping  15 days 11/9/2004 12/10/2004  
    Meetings 2 days 11/9/2004 11/10/2004 Bryan
    Assign team goals/roles/responsibilites 0.25 days 11/11/2004 11/11/2004 Bryan
    Create system for organizing team documents 0.25 days 11/11/2004 11/11/2004 Bryan
    On site customer interview 1 day 11/11/2004 11/16/2004 Bryan
    Problem statement 0.25 days 11/16/2004 11/16/2004 Bryan
    Constraints list 0.25 days 11/16/2004 11/16/2004 Bryan
    Preliminary research (lean,SMED) 7 days 11/17/2004 12/3/2004 Bryan
    Web page development 3 days 12/7/2004 12/9/2004 Bryan
    Equipment pick up from HP 1 day 12/10/2004 12/10/2004 Bryan
    PHASE 2 - Conceptual Power Design 2 days 12/28/2004 12/29/2004  
    Research 2005 NEC (Motor Section) 1 day 12/28/2004 12/28/2004 Bryan
    Define options for power delivery and control 1 day 12/29/2004 12/29/2004 Bryan
    PHASE 3 - Preliminary Power Design 2 days 12/30/2004 1/7/2005  
    Research motor starters 0.5 days 12/30/2004 12/30/2004 Bryan
    Research contactors 0.5 days 12/30/2004 12/30/2004 Bryan
    Research overload relays 0.5 days 1/7/2005 1/7/2005 Bryan
    Research fused disconnect means 0.5 days 1/7/2005 1/7/2005 Bryan
    PHASE 4 - Detailed Power Design 3 days 1/8/2005 1/21/2005  
    Create Power Requirements Document 3 days 1/8/2005 1/21/2005 Bryan
    PHASE 5 - Conceptual Cell Design 15.5 days 1/22/2005 3/11/2005  
    Create detailed cell requirements 0.5 days 1/22/2005 1/22/2005 Bryan/Charlie
    Update web page 1 day 1/22/2005 1/28/2005 Bryan
    PLC Testing 5 days 1/28/2005 2/11/2005  
    Research PLC  3 days 1/28/2005 2/3/2005 Bryan
    Purchase PLC programmer and software 1 day 2/3/2005 2/4/2005 Bryan
    Run test program in PLC 1 day 2/4/2005 2/11/2005 Bryan
    Pneumatics Testing 4 days 2/11/2005 2/26/2005  
    Research pneumatics and equipment 2 days 2/11/2005 2/18/2005 Bryan
    Purchase hosing/connects to make PLC/pneumatic test bench 1 day 2/18/2005 2/25/2005 Bryan
    Create PLC/pneumatic test bench 1 day 2/25/2005 2/26/2005 Bryan
    Preliminary parts list 1 day 2/26/2005 3/1/2005 Bryan
    Preliminary budget estimate 1 day 3/1/2005 3/2/2005 Bryan
    Create Power Point presentation 2 days 3/2/2005 3/4/2005 Bryan
    Design Review 1 day 3/4/2005 3/11/2005 Bryan
    PHASE 6 - Preliminary Cell Design 8.5 days 3/11/2005 4/9/2005  
    Spec pneumatic valving, hosing, etc 1 day 3/11/2005 3/12/2005 Bryan
    Specify end effectors 1 day 3/12/2005 3/18/2005 Bryan
    Prelim design of workcell actuator and mounting 3 days 3/18/2005 4/1/2005 Bryan
    Prelimininary design of dc panel 1 day 4/1/2005 4/6/2005 Bryan
    Preliminary design of operator control panel 0.5 days 4/6/2005 4/6/2005 Bryan
    Create sequence of operations for PLC 1 day 4/8/2005 4/8/2005 Bryan
    Finalized budget and work plan 1 day 4/9/2005 4/9/2005 Bryan
    PHASE 7 - Detail Cell Design 8 days 4/13/2005 5/4/2005  
    Create PLC panel drawing 1 day 4/13/2005 4/13/2005 Bryan
    Create operator control panel drawing 0.5 days 4/15/2005 4/15/2005 Bryan
    Create drawings of various mounting brackets 1 day 4/15/2005 4/20/2005 Bryan
    Create drawing for actator mounting assembly 1 day 4/20/2005 4/22/2005 Bryan
    Detailed parts list 0.5 days 4/22/2005 4/22/2005 Bryan
    Create ladder diagram for PLC 2 days 4/23/2005 4/27/2005 Bryan
    Purchase orders prepared and issued 1 day 4/29/2005 4/29/2005 Bryan
    Web page update 1 day 5/4/2005 5/4/2005 Bryan
    PHASE 8 - Cell Fabrication/Assembly 8 days 5/6/2005 5/25/2005  
    Install belt and test AC portion of system 1 day 5/6/2005 5/6/2005 Bryan/Charlie/HP
    Assemble PLC panel  2 days 5/7/2005 5/11/2005 Bryan
    Assemble operator control panel (OCP) 1 day 5/13/2005 5/13/2005 Bryan
    Assemble two actuator mounting assemblies 2 days 5/18/2005 5/20/2005 Charlie/Brad?
    Mount actuators, PLC panel, OCP, and other components 1 day 5/21/2005 5/21/2005 Bryan/Charlie/Brad
    Wire field devices 1 day 5/25/2005 5/25/2005 Bryan
    PHASE 9 - Overall System Testing 2 days 5/27/2005 6/1/2005  
    Collection of performance data, analysis, and design evalulation 2 days 5/27/2005 6/1/2005 Bryan/Charlie
    PHASE 10 - Delivery 2.25 days 6/4/2005 6/11/2005  
    Create final design report 2 days 6/4/2005 6/8/2005 Bryan
    Web page update 0.25 days 6/11/2005 6/11/2005 Bryan

     

  •  

     

     