Senior Design Project (Summer - Fall 2006)

Milestones

Affiliates
 

final



Create a headlight system that will easily mount to a JPL land rover and display enough illumination for the rover imaging system to take stereo images and create detailed range maps of the outlying terrain during nigttime driving.
ME

ISGC

NASA

JPL

 

 

11 December 2006.  All Deliverables Due By COB

9 December 2006.  Commencement Day

1 December 2006.  Snapshot Day

28 November 2006.  Finish Reflector Machining Including Welding

20 - 24 November 2006.  Work on Final Paper During Break

12 November 2006.  Create Outline for Final Paper

7 November 2006.  Start Manufacturing Reflector

31 October 2006.  Finalized Reflector Design

23 October 2006.  Start Research and Design of Reflector

19 October 2006.  ISGC Symposium/Design Review Presentation

13 October 2006.  Start Building Test Frame and Mount LED To Heat Sink

3 October 2006.  Recieved Cameras, Lenses, and Mounts

25 September 2006.  Recieved LED and Ordered Heat Sink

2 August 2006. Snapshot Day.

12 July 2006.   Design Review.


   
 

 

 
 
 